Art. 3 Regulation (EU) 2023/1184

Rules for counting electricity obtained from direct connection to an installation generating renewable electricity as fully renewable

In forcesince 10 Jun 2024cited 7×

For the purpose of demonstrating compliance with the criteria set out in Article 27(3), fifth subparagraph of Directive (EU) 2018/2001 for counting electricity obtained from direct connection to an installation generating renewable electricity as fully renewable, the fuel producer shall provide evidence on the following:

(a)

the installations generating renewable electricity are connected to the installation producing renewable fuel of non-biological origin via a direct line, or the renewable electricity production and production of renewable fuel of non-biological origin take place within the same installation;

(b)

the installations generating renewable electricity came into operation not earlier than 36 months before the installation producing renewable fuel of non-biological origin; where additional production capacity is added to an existing installation producing renewable fuel of non-biological origin, the added capacity shall be considered to be part of the existing installation, provided that the capacity is added at the same site and the addition takes place no later than 36 months after the initial installation came into operation;

(c)

the installation producing electricity is not connected to the grid, or the installation producing electricity is connected to the grid but a smart metering system that measures all electricity flows from the grid shows that no electricity has been taken from the grid to produce renewable fuel of non-biological origin.

If the fuel producer also uses electricity from the grid, it may count it as fully renewable if it complies with the rules set out in Article 4.