The Commission rejected this claim, on the basis of the following statements that had been made by the PGTEX Group in the course of the investigation. First, in its reply to the deficiency letter [Deficiency reply concerning PGTEX Morocco SARL: Reply to question 7, page 20.], the PGTEX Group only referred to the plant – phase 1 for its production, its storage of raw materials and finished products, and the administrative area. Second, in its reply to the deficiency letter [Deficiency reply concerning PGTEX Morocco SARL: Reply to question 6 c, page 20.], the PGTEX Group stated that its GFF machines, which were running in 2020, were all located in plant – phase 1. Consequently, the Commission deducted that none of these machines, which were operational in 2020, were located in plant – phase 2. This was also corroborated by other statements of the PGTEX Group in its deficiency reply. [Deficiency reply concerning PGTEX Morocco SARL: Reply to question 9 m, ii, page 23.]
93 2. RESULTS OF THE INVESTIGATION › 2.6. Value of parts and added value, Regulation (EU) 2022/301
In forcesince 24 Feb 2022cited 1×
Judgment of the General Court (Tenth Chamber, Extended Composition) of 4 December 2024. PGTEX Morocco v European Commission.Decision
However, as is apparent from recital 93 of the contested implementing regulation, ‘the Commission rejected this claim, on the basis of the following statements that had been made by the PGTEX Group in the course of the investigation’. …
4 Dec 2024 · 62022TJ0246