31 3. ASSESSMENT › 3.2. COMPETITIVE ASSESSMENT › 3.2.2. GEOGRAPHIC MARKET DEFINITION, Decision_act (EU) 2022/1376

In forcesince 26 Jul 2022

In 2006, the Commission has in a merger decision defined [Commission Decision 2007/353/EC of 14 March 2006 declaring a concentration compatible with the common market and the functioning of the EEA Agreement (Case COMP/M.3868 – DONG/Elsam/Energi E2) (OJ L 133, 25.5.2007, p. 24), paragraphs 258-260.] two separate geographic markets for electricity wholesale: that of East Denmark (‘DK2’) and that of West Denmark (‘DK1’), as at the time there was no direct interconnection between the two Danish bidding (or price) areas. The Commission reached the same conclusion in the DE/DK Interconnector decision in 2018 [Summary of Commission Decision of 7 December 2018 relating to a proceeding under Article 102 of the Treaty on the Functioning of the European Union and Article 54 of the EEA Agreement (Case AT.40461 – DK/DE Interconnector) (OJ C 58, 14.2.2019, p. 7), paragraphs 49-50.].