Recital 23, Decision_act (EU) 2022/403

In forcesince 3 Mar 2022

Furthermore, Rowerland disagreed with the Commission’s revision of the electricity costs stated in recitals (15)(e)(i) and 15(e)(iii). It claimed that its allocation key used for electricity was selected by a certified auditor. No evidence was submitted in this regard. Therefore, the claim was rejected.