Art. 4 Directive (EU) 2021/1187

Designated Authority

In forcecited 2×
1.

By 10 August 2023, each Member State shall designate, at the appropriate administrative level, the authorities that are to act as a designated authority.

2.

A Member State may, where relevant, designate different authorities as the designated authority depending on the project or category of projects, transport mode, or the geographical area. In such a case, the Member State shall ensure that there is only one designated authority for a given project and for a given permit-granting procedure.

3.

Member States shall take all necessary measures to provide project promoters with easily available information about the identity of the designated authority for a given project.

4.

Member States may empower the designated authority to take the authorising decision.

When empowered to take the authorising decision in accordance with the first subparagraph, the designated authority shall verify that all the permits, decisions and opinions necessary for the adoption of the authorising decision have been obtained and shall notify the authorising decision to the project promoter.

5.

Where the designated authority is not empowered to take the authorising decision, Member States shall take the necessary measures to ensure that the project promoter is notified of the adoption of the authorising decision.

6.

Member States may empower the designated authority to establish indicative time-limits for different intermediary steps of the permit-granting procedure in accordance with Article 5(1), without prejudice to the four-year time-limit referred to in that paragraph.

7.

The designated authority shall:

(a)

be the point of contact for information for the project promoter and for other relevant authorities involved in the procedure leading to the authorising decision for a given project;

(b)

provide the project promoter, where required to do so under national law, with the detailed application outline referred to in Article 6(4), including information on the indicative time-limits relating to the permit-granting procedures, in accordance with the four-year time-limit referred to in Article 5(1);

(c)

oversee the timeframe of the permit-granting procedure, and in particular record any extension of the time-limit referred to in Article 5(4);

(d)

if requested, provide guidance to the project promoter concerning the submission of all relevant information and documents, including all the permits, decisions and opinions which have to be obtained and provided for the authorising decision.

The designated authority may also provide guidance to the project promoter as to what additional information and/or documents should be delivered in the event that the notification referred to in Article 6(1) has been rejected.

8.

Paragraph 7 is without prejudice to the competence of any other authorities involved in the permit-granting procedure and to the possibility for the project promoter to contact the individual authorities for the specific permits, decisions or opinions which form part of the authorising decision.

  • Umweltverträglichkeitsprüfungsgesetz 200024Law

    … 5 sowie benannte Behörde im Sinne des Art. 4 der Richtlinie (EU) 2021/1187, der die Aufgaben des Art. 4 und des Art. 7 dieser Richtlinie obliegen. Für den Vollzug der Strafbestimmungen ist die Bezirksverwaltungsbehörde zuständig. (3) …

  • Schifffahrtsgesetz71Law

    … der Bundesminister für Innovation, Mobilität und Infrastruktur ist benannte Behörde iSd Art. 4 der Richtlinie (EU) 2021/1187, dieser obliegen die Aufgaben nach dem Art. 4 und des Art. 7 dieser Richtlinie.