Art. 28 Regulation (EU) 2016/1447

Energisation and synchronisation of HVDC converter stations

In forcesince 26 Aug 2016cited 2×

Unless otherwise instructed by the relevant system operator, during the energisation or synchronisation of an HVDC converter station to the AC network or during the connection of an energised HVDC converter station to an HVDC system, the HVDC converter station shall have the capability to limit any voltage changes to a steady-state level specified by the relevant system operator in coordination with the relevant TSO. The level specified shall not exceed 5 per cent of the pre-synchronisation voltage. The relevant system operator, in coordination with the relevant TSO, shall specify the maximum magnitude, duration and measurement window of the voltage transients.

  • Netcode elektriciteit6.16Law

    … wel gedurende de aansluiting van een onder spanning gebracht HVDC-convertorstation op een HVDC-systeem, als bedoeld in artikel 28 van de Verordening (EU) 2016/1447 (NC HVDC), de spanningsschommelingen te beperken tot de grenswaarden voor …

  • Systeemcode elektriciteit 20266.16Law

    … dan wel gedurende de aansluiting van een onder spanning gebracht HVDC-convertorstation op een HVDC-systeem, bedoeld in artikel 28 van Verordening (EU) 2016/1447 (NC HVDC), de spanningsschommelingen te beperken tot de grenswaarden voor …