The relevant TSO in coordination with the relevant system operator may agree with a demand facility owner or a CDSO (including, but not restricted to, through a third party) on a contract for the delivery of demand response very fast active power control.
If the agreement referred to in paragraph 1 takes place, the contract referred to in paragraph 1 shall specify:
a change of active power related to a measure such as the rate-of-change-of-frequency for that portion of its demand;
the operating principle of this control system and the associated performance parameters;
the response time for very fast active power control, which shall not be longer than 2 seconds.