1.

The Agency shall assess the efficiency of current bidding zone configuration every three years.

It shall:

(a)

request ENTSO for Electricity to draft a technical report on current bidding zone configuration; and

(b)

draft a market report evaluating the impact of current bidding zone configuration on market efficiency.

2.

The technical report referred to in paragraph 1 second subparagraph point (a) shall include at least:

(a)

a list of structural congestion and other major physical congestion, including locations and frequency;

(b)

an analysis of the expected evolution or removal of physical congestion resulting from investment in networks or from significant changes in generation or in consumption patterns;

(c)

an analysis of the share of power flows that do not result from the capacity allocation mechanism, for each capacity calculation region, where appropriate;

(d)

congestion incomes and firmness costs;

(e)

a scenario encompassing a ten year time-frame.

3.

Each TSO shall provide data and analysis to allow the technical report on current bidding zone configuration to be produced in a timely manner.

4.

ENTSO for Electricity shall deliver to the Agency the technical report on current bidding zone configuration no later than nine months after the request by the Agency.

5.

The technical report on current bidding zone configuration shall cover the last three full calendar years preceding the request by the Agency.

6.

Without prejudice to the confidentiality obligations provided for in Article 13, ENTSO for Electricity shall make the technical report available to the public.

7.

If the technical or market report reveals inefficiencies in the current bidding zone configuration, the Agency may request TSOs to launch a review of an existing bidding zone configuration in accordance with Article 32(1).

  • Regulation (EU) 2019/943Law

    … В членове 32 и 34 от Регламент (ЕС) 2015/1222 се определят правила относно прегледа на конфигурацията на пазарните зони, в членове 41 и 54 от …

  • Judgment of the General Court (Seventh Chamber) of 24 October 2019. Energie-Control Austria für die Regulierung der Elektrizitäts- und ErdgaDecision

    On 17 November 2016, ACER adopted Decision No 6/2016 regarding the determination of capacity calculation regions. Article 1 of Decision No 6/2016 and Annex I thereto determine the capacity calculation regions in accordance with Article 15 …

    24 Oct 2019 · 62017TJ0332

  • Judgment of the General Court (Seventh Chamber) of 24 October 2019. Austrian Power Grid AG and Vorarlberger Übertragungsnetz GmbH v EuropeanDecision

    On 17 November 2016, ACER adopted Decision No 6/2016 regarding the determination of capacity calculation regions. Article 1 of Decision No 6/2016 and Annex I thereto determine the capacity calculation regions in accordance with Article 15 …

    24 Oct 2019 · 62017TJ0333

  • Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on…Law

    … Articles 32 and 34 of Regulation (EU) 2015/1222 set out rules on review of bidding zone configuration, Articles 41 and 54 thereof set out harmonised limits on maximum and minimum clearing prices for day-ahead and intraday timeframes, …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 1 October 2025. Bundesnetzagentur für Elektrizität, Gas, TelekommunikDecision

    … Mit den folgenden, hilfsweise geltend gemachten Klagegründen wird zweitens ein Verstoß gegen die Art. 32 bis 34, Art. 25 und Art. 29 Abs. 3 Buchst. b der Verordnung 2015/1222 beanstandet, drittens ein Verstoß gegen Art. 21 Abs. 2 …

    1 Oct 2025 · 62023TJ0600

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. TransnetBW GmbH v European Union Agency for the CoDecision

    By its third plea, the applicant, supported by the Federal Republic of Germany and Amprion, claims that the penalisation of loop flows above the threshold, pursuant to the priority list established by Article 7(6) of the contested cost …

    25 Sep 2024 · 62021TJ0476

  • Arrêt du Tribunal (septième chambre) du 20 septembre 2018. Mondi AG contre Agence de coopération des régulateurs de l’énergie.Decision

    Le 17 novembre 2016, l’ACER a adopté la décision n o 06/2016, relative à la détermination des régions pour le calcul de la capacité (ci-après la « décision 6/2016 »). L’article 1 er et l’annexe I de la décision 6/2016 …

    20 Sep 2018 · 62017TJ0146

  • Arrêt du Tribunal (septième chambre) du 20 septembre 2018. Exaa Abwicklungsstelle für Energieprodukte AG contre Agence de coopération des réDecision

    Le 17 novembre 2016, l’ACER a adopté la décision n o 06/2016, relative à la détermination des régions pour le calcul de la capacité (ci-après la « décision 6/2016 »). L’article 1 er et l’annexe I de la décision 6/2016 …

    20 Sep 2018 · 62017TJ0123