20 2. DESCRIPTION OF THE AID MEASURES › 2.3. The contracts, Decision_act (EU) 2015/1877

In forcesince 20 Apr 2015

On 15 July 2008 by note number 7323, Termoelectrica stated the following: ‘(…) Termoelectrica SA has analysed several methods of solving this urgent problem and the only variant with any prospect of rapid success and that does not require EU approval is the following: Signature of a long-term (10 year) contract between Termoelectrica SA and Hidroelectrica SA for the purchase of the electricity produced by generation unit no 4 of CET Paroșeni. The contract price will be the price for CET Paroșeni established by ANRE on the regulated market, based on the justified costs of Termoelectrica SA; and Signature with Compania Națională a Huilei Petroșani of a long-term (approx. 10 year) contract to acquire coal. For Termoelectrica SA (SE Paroșeni) and even for the Compania Națională a Huilei [On 1 August 2013, Societatea Națională a Huilei, which resulted from the spin-off from Compania Nationala a Huilei allegedly competitive mines, was also incorporated into Complexul Energetic Hunedoara.], this (…) would ensure the long-term future of the two companies located in the Jiu Valley.’