17 2. DESCRIPTION OF THE AID MEASURES › 2.2. Other market information, Decision_act (EU) 2015/1877

In forcesince 20 Apr 2015

The Romanian market is interconnected with, notably, Bulgaria, with 400 MW net transfer capacity in 2009-2010 and Hungary, with 500-800 MW net transfer capacity in 2009-2010. The net capacity of interconnection with these Member States was not fully used in that period, due to congestion. During the period 2009-2011, the flux of imports and exports of electricity into and from Romania were as follows: (i) in 2009, imports of electricity amounted to 676 GWh, while exports amounted to 3154 GWh (approximately 4,8 % of the all the electricity produced in Romania); (ii) in 2010, imports of electricity amounted to 943 GWh, while exports amounted to 3854 GWh (approximately 3,4 % of the all the electricity produced in Romania); (iii) in 2011, imports of electricity amounted to 1036 GWh, while exports amounted to 2942 GWh (approximately 2,8 % of all the electricity produced in Romania).