Aid for backhaul network deployment shall be compatible with the internal market pursuant to Article 107(3) of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty, provided that the conditions laid down in this Article and in Chapter I are fulfilled.
The eligible costs shall be all costs for the construction, management and operation of a backhaul network. The maximum aid amount for a project shall be established on the basis of a competitive selection process as set out in paragraph 6, point (a). Where an investment is carried out in accordance with paragraph 6, point (b), without a competitive selection process, the aid amount shall not exceed the difference between the eligible costs and the normal operating profit of the investment. The operating profit shall be deducted from the eligible costs ex ante on the basis of reasonable projections and verified ex post through a claw-back mechanism. The reasonable projection of the measure requires that all costs and all revenues, which are expected to be incurred over the economic lifetime of the investment, shall be taken into account.
Backhaul network deployment shall be located in areas where there is no backhaul network based on fibre or on other technologies able to provide the same level of performance and reliability as fibre existing or credibly planned to be deployed within the relevant time horizon. This shall be verified by mapping and public consultation in accordance with paragraph 4.
The mapping and public consultation for the purposes of paragraph 3 shall meet the following requirements cumulatively:
the mapping shall identify the target areas for the backhaul State intervention and shall take into account all existing backhaul networks. All the elements of the methodology and the underlying technical criteria used to map the target areas must be made publicly available. Mapping shall always be verified through a public consultation;
the public consultation shall be carried out by the competent public authority through the publication of the main characteristics of the planned State intervention and the list of areas identified in the mapping exercise in accordance with point (a). That information must be made available on a publicly accessible website at regional and national level. The public consultation shall invite interested parties to comment on the planned State intervention and to submit substantiated information in accordance with point (a) regarding the backhaul networks existing or credibly planned to be deployed within the relevant time horizon. The public consultation shall last at least 30 days.
The intervention shall bring a significant improvement (step change) compared to the backhaul networks existing or credibly planned to be deployed within the relevant time horizon, as identified through mapping and public consultation carried out in accordance with paragraph 4. Credibly planned networks shall be taken into account for the assessment of the step-change only if they would, on their own, provide similar performance to that of the planned State funded network in the target areas within the relevant time horizon. A step change takes place if, as a result of the subsidised intervention, a significant new investment in the backhaul network is undertaken and the subsidised backhaul network is based on fibre or on other technologies able to provide the same level of performance of fibre, as opposed to the existing or credibly planned networks within the relevant time horizon. The intervention must include more than 70 % investment in broadband infrastructure.
The aid shall be granted as follows:
the aid shall be allocated on the basis of an open, transparent and non-discriminatory competitive selection procedure in line with the principles of public procurement rules and respecting the principle of technology neutrality, based on the most economically advantageous offer;
when the aid is granted without a competitive selection procedure to a public authority to deploy and manage, directly or through an in-house entity, a backhaul network, the public authority or the in-house entity, as the case may be, shall provide only wholesale services using the subsidised network. Any concession or other entrustment to a third party to build or operate the network shall be allocated through an open, transparent and non-discriminatory competitive selection procedure, in line with the principles of public procurement rules and respecting the principle of technology neutrality, based on the most economically advantageous offer.
The operation of the subsidised network shall offer wholesale access, as defined in Article 2, point (139), under fair and non-discriminatory conditions to both fixed and mobile networks. Active wholesale access shall be granted for at least 10 years from the start of the operation of the network and the wholesale access to the broadband infrastructure shall be granted for the lifetime of the elements concerned. The same access conditions shall apply to the entirety of the network, including on parts of the network where existing infrastructures have been used. The access obligations shall be enforced irrespective of any change in ownership, management or operation of the network. The State funded network shall cater for all fixed and mobile networks in the target areas of the backhaul intervention and shall make available at least 50 % of the capacity to access seekers. In order to render the wholesale access effective and to enable the access seekers to provide services, wholesale access shall also be granted to parts of the network that have not been State funded or that may not have been deployed by the aid beneficiary, such as by granting access to active equipment even if only broadband infrastructure is financed.
The wholesale access price shall be based on one of the following benchmarks and pricing principles:
the average published wholesale prices that prevail in other comparable, more competitive areas of the Member State;
the regulated prices already set or approved by the national regulatory authority for the markets and services concerned; or
cost orientation or a methodology mandated in accordance with the sectorial regulatory framework.
Without prejudice to the competences of the national regulatory authority under the regulatory framework, the national regulatory authority shall be consulted on wholesale access products, the terms and conditions for access, including on prices, and on disputes related to the application of this Article.
Member States shall put in place a monitoring and claw-back mechanism if the amount of aid granted to a project exceeds EUR 10 million.
To ensure that aid remains proportional and does not lead to overcompensation or cross-subsidisation of non-aided activities, the aid beneficiary shall ensure accounting separation between the funds used for the deployment and the operation of the State funded network and other funds at its disposal.