Art. 10 Directive (EU) 2014/25

Water

In forcesince 26 Feb 2014cited 7×
1.

As far as water is concerned, this Directive shall apply to the following activities:

(a)

the provision or operation of fixed networks intended to provide a service to the public in connection with the production, transport or distribution of drinking water;

(b)

the supply of drinking water to such networks.

2.

This Directive shall also apply to contracts or design contests awarded or organised by contracting entities which pursue an activity referred to in paragraph 1 and which are connected with one of the following:

(a)

hydraulic engineering projects, irrigation or land drainage, provided that the volume of water to be used for the supply of drinking water represents more than 20 % of the total volume of water made available by such projects or irrigation or drainage installations,

(b)

the disposal or treatment of sewage.

3.

The supply, by a contracting entity other than a contracting authority, of drinking water to fixed networks which provide a service to the public shall not be considered to be a relevant activity within the meaning of paragraph 1 where all of the following conditions are met:

(a)

the production of drinking water by that contracting entity concerned takes place because its consumption is necessary for carrying out an activity other than those referred to in Articles 8 to 11;

(b)

the supply to the public network depends only on that contracting entity’s own consumption and has not exceeded 30 % of that contracting entity’s total production of drinking water, on the basis of the average for the preceding three years, including the current year.

  • Judgment of the Court (Grand Chamber) of 21 December 2023. Infraestruturas de Portugal, SA and Futrifer Indústrias Ferroviárias, SA v TosccaDecision

    In that connection, it should be observed that, in accordance with Article 1(2) and Article 11 of Directive 2014/25, procurement within the meaning of that directive is the acquisition by means of a supply, works or service contract of …

    21 Dec 2023 · 62022CJ0066

  • Judgment of the Court (Fifth Chamber) of 28 October 2020. Pegaso Srl Servizi Fiduciari and Others v Poste Tutela SpA.Decision

    Articles 8 to 14 of Directive 2014/25 list the activities to which that directive applies. Those activities are gas and heat (Article 8), electricity (Article 9), water (Article 10), transport services (Article 11), ports and airports …

    28 Oct 2020 · 62018CJ0521

  • Opinion of Advocate General Bobek delivered on 23 April 2020. Pegaso Srl Servizi Fiduciari and Others v Poste Tutela SpA.Decision

    By contrast, the scope of application of the Utilities Directive is primarily defined materially, by reference to the nature of the activities. [See Articles 1(2) and 4(1) of the Utilities Directive.] Those activities are referred to in …

    23 Apr 2020 · 62018CC0521

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 12 September 2024. DYKA Plastics NV v Fluvius System Operator CV.Decision

    However, I believe that that assertion requires verification by the referring court [Among other factors, the referring court must determine whether, by reason of their amount, the contracts exceed the minimum threshold to which the …

    12 Sep 2024 · 62023CC0424

  • Wet hergebruik van overheidsinformatie1Law

    … elektriciteit, voor zover artikel 9 van Richtlijn 2014/25/EU daarop van toepassing is; 3°. water, voor zover artikel 10 van Richtlijn 2014/25/EU daarop van toepassing is; 4°. het ter beschikking stellen of exploiteren van netten bestemd …

  • Judgment of the Court (Fourth Chamber) of 16 January 2025. DYKA Plastics NV v Fluvius System Operator CV.Decision

    However, Article 10(1) of Directive 2014/25/EU of the European Parliament and of the Council of 26 February 2014 on procurement by entities operating in the water, energy, transport and postal services sectors and repealing Directive …

    16 Jan 2025 · 62023CJ0424

  • Opinion of Advocate General Rantos delivered on 11 May 2023. CRRC Qingdao Sifang Co. Ltd and Astra Vagoane Călători SA v Autoritatea pentru Decision

    Under Article 7 thereof, entitled ‘Contracts in the water, energy, transport and postal services sectors’, Directive 2014/24 is not to apply to public contracts and design contests which, under Directive 2014/25/EU of the European …

    11 May 2023 · 62022CC0266