In the course of the investigation, some of the Autonomous Communities submitted internal calculations comparing the costs of using both technologies to extend the coverage. However, in addition to uncertainty about the date of these calculations, none of them was detailed and robust enough to justify the choice of terrestrial technology to extend the coverage. What is more, none of them was carried out by an independent expert.
157 5. LEGAL ASSESSMENT › 5.3. COMPATIBILITY ASSESSMENT › 5.3.3. Article 107(3)(c) TFEU › 5.3.3.2. Well-defined aid › Technological neutrality, appropriateness and proportionality of the measure, Decision_act (EU) 2014/489
Judgment of the General Court (Fifth Chamber) of 26 November 2015. Kingdom of Spain v European Commission.Decision
In that regard, it should be observed that, contrary to the Kingdom of Spain’s assertion, the rejection of the calculations submitted by certain Autonomous Communities during the procedure before the Commission was not based on the study …
26 Nov 2015 · 62013TJ0461
Judgment of the Court (Fourth Chamber) of 20 December 2017. Kingdom of Spain v European Commission.Decision
Moreover, the Kingdom of Spain’s argument can be summarised as contesting the assertion, in paragraph 104 of the judgment under appeal, that the Commission was not required to provide more details as regards the non-compliance with the …
20 Dec 2017 · 62016CJ0081
Opinion of Advocate General Wathelet delivered on 7 September 2017. Comunidad Autónoma del País Vasco and Others v European Commission.Decision
SES Astra contends, in essence, for the same reasons as those put forward by the Commission, that this part of the fourth plea is manifestly inadmissible. In addition, in the event that the Court should decide that the SGEI at issue was …
7 Sep 2017 · 62016CC0066