If the requested court is not in a position to execute the request within 90 days of receipt, it shall inform the requesting court thereof, using form G in the Annex. When it does so, the grounds for the delay shall be given as well as the estimated time that the requested court expects it will need to execute the request.
Art. 15 Council Regulation (EC) No 1206/2001 of 28 May 2001 on cooperation between the courts of…
Notification of delay
In forcesince 4 Dec 2008
Changed on 4 Dec 2008
Notification of delay
- 4 Dec 2008 – todayin force
- 28 May 2001 – 4 Dec 2008earlier wording