In its decision of 14 October 1998 initiating the formal investigation procedure, the Commission requested evidence that the prices were market prices, in particular because it had the following indications to the contrary:

(a)

a private utility would not have entered into a contract to provide basic process utilities at fixed prices over 30 years, when at the same time LLG had the option to terminate the contract already after five years;

(b)

in its ERDF cofinancing application, Austria had indicated that the Province of Burgenland would have to provide grants to the utility operator WHS to cover expected negative cash flows from the provision of basic process utilities to LLG.