The building control authority may specify that a particular type of controlled change is a notifiable change or a major change, in relation to specified work, by giving notice in writing to that effect to the client, principal contractor (or sole contractor) and the principal designer (or sole or lead designer) for that work.
The Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025, 25
Change control: the building control authority’s power to specify notifiable changes and major changes
In forcesince 12 Dec 2025cited 2×
The Building (Local Authority Charges) Regulations 20105Law
… under the following regulations of the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025— (i) regulations 20 to 25 (a “controlled change charge”); (ii) regulations 39 to 43 (a “completion certificate …
The Building etc. (Amendment) (No. 2) (Wales) Regulations 202516Law
… under the following regulations of the Building (Higher-Risk Buildings Procedures) (Wales) Regulations 2025— (i) regulations 20 to 25 (a “controlled change charge”); (ii) regulations 39 to 43 (a “completion certificate …