In regulation 2(1) (interpretation) at the appropriate places insert the following definitions—

“the 1990 Act” means the Town and Country Planning Act 1990;

;

“devolved combustion plant” means a combustion plant in Wales with a related electrical output of between 300 and 350 megawatts;

;

“local planning authority” and “planning permission” have the meanings given in section 336 of the 1990 Act;

;

“relevant planning authority” means in relation to a relevant planning permission—

where the development to which the application relates is of national significance for the purposes of section 62D of the 1990 Act, the Welsh Ministers;

in all other cases, the local planning authority;

;

“relevant planning permission” means a planning permission—

for the construction of a devolved combustion plant; or

for an extension or alteration to a combustion plant in Wales which will have the effect of increasing the rated electrical output of the plant to between 300 and 350 megawatts;

.