In regulation 2 (interpretation)—
in the definition of “distribution system” for “has the meaning given by” substitute “means a system, other than a private network, of the type described in”;
insert at the appropriate place—
“private network” means a network for the distribution of electricity which is not operated by a person authorised to distribute electricity under a licence granted or treated as granted under section 6(1)(c) of the Electricity Act 1989;
;
“target commissioning date” means the intended date, being a date within the target commissioning window, for the generation of electricity to begin by a CFD unit once it is established or altered;
;
“target commissioning window” means the period in which the generation of electricity must take place by a CFD unit once it is established or altered, the duration of which is listed in the allocation framework for each type of eligible generating station;
;
“target commissioning window start date” means the date on which the target commissioning window begins;
;
“target dates” means the target commissioning date and the target commissioning window start date;
;
for the definition of “working day”, substitute—
“working day” means a day that is not a Saturday or Sunday, Christmas Day, Good Friday or any day that is a bank holiday in England and Wales under the Banking and Financial Dealings Act 1971.
.