The Self-build and Custom Housebuilding (Time for Compliance and Fees) Regulations 2016, 2

Time for compliance with duty to grant planning permission

In force

The time allowed for an authority to which section 2A of the Act (duty to grant planning permission etc) applies to comply with the duty under subsection (2) of that section in relation to any base period is the period of 3 years beginning immediately after the end of that base period.