The Contracts for Difference (Standard Terms) Regulations 2014, 3

Provision to be included in standard terms

In forcesince 15 Apr 2026cited 4×
(1)

The standard terms issued under section 11(1) of the Act or revised under section 11(2) of the Act must set out—

(a)

that where a strike price is higher than a reference price, the CFD counterparty must pay the generator the difference between the strike price and the reference price …;

(aa)

any circumstances in which the CFD counterparty is not required to pay the generator the amount, or the full amount, specified under paragraph (a);

(b)

that where a reference price is higher than a strike price, the generator must pay the CFD counterparty the difference between the reference price and the strike price;

(c)

that the amount payable under paragraph (a) or (b) must be calculated by reference to the amount of low carbon electricity generation produced by a generating facility;

(d)

the way in which a reference price is to be determined;

(e)

the way in which a strike price is to be adjusted according to inflation;

(f)

the way in which the amount of low carbon electricity generation produced by a generating facility is to be determined;

(g)

that sums must not be paid by the CFD counterparty under a CFD where those sums are not allocated to that CFD in accordance with the Contracts for Difference (Supplier Obligation) Regulations 2014;

(h)

which circumstances allow a generator to reduce the capacity of its generating facility;

(i)

which changes in law will cause compensation to be payable by one party to the other party or cause a change to a strike price;

(j)

the way in which the amount of compensation payable or a change to a strike price under paragraph (i) is to be determined;

(ja)

which circumstances will allow for a payment under a CFD to be adjusted by reference to the generator’s fulfilment, or non-fulfilment, of the obligations set out in a sustainable industry reward statement …;

(k)

which time limits in a CFD may be extended where force majeure prevents a party from complying with them;

(l)

which circumstances require a generator to receive the consent of the CFD counterparty before transferring a CFD or assigning its rights and obligations under a CFD;

(m)

the way in which the parties to a CFD may amend a CFD;

(n)

a mechanism by which disputes between the parties to a CFD are to be resolved;

(o)

which circumstances allow the CFD counterparty to terminate a CFD;

(p)

which circumstances require a generator to make a payment to the CFD counterparty following termination of a CFD; and

(q)

the way in which the amount payable under paragraph (p) is to be determined.