The River Mersey (Mersey Gateway Bridge) Order 2011, 5

Power to deviate

In forcesince 11 Jan 2011

In constructing or maintaining any of the scheduled works, the undertaker may—

(a)

deviate laterally from the lines or situations shown on the works plans to the extent of the limits of deviation for that work; and

(b)

deviate vertically from the levels shown on the sections—

(i)

to any extent not exceeding 3 metres upwards; or

(ii)

to any extent downwards as may be found to be necessary or convenient.