The Electricity (Applications for Consent) Amendment (Scotland) Regulations 2013, 2

Amendment of the Electricity (Applications for Consent) Regulations 1990

In force
(1)

The Electricity (Applications for Consent) Regulations 1990 are amended in accordance with paragraph (2).

(2)

In regulation 11(1) (fees payable on applications for consent) for the Table substitute—

TABLE

Subject matter of application for consent | Fee

1.

Overhead line with a total distance not exceeding 15 kilometres which is not EIA development | £180

2.

Overhead line with a total distance not exceeding 15 kilometres which is EIA development | £2,400

3.

Overhead line with a total distance— |

exceeding 15 kilometres but not exceeding 50 kilometres

| £18,000

exceeding 50 kilometres but not exceeding 100 kilometres

| £30,000

exceeding 100 kilometres

| £60,000

4.

Construction or construction and operation of a generating station of capacity— |

not exceeding 10 megawatts

| £6,000

exceeding 10 megawatts but not exceeding 100 megawatts

| £18,000

exceeding 100 megawatts but not exceeding 200 megawatts

| £24,000

exceeding 200 megawatts but not exceeding 500 megawatts

| £36,000

exceeding 500 megawatts

| £60,000

5.

Extension or extension and operation of a generating station resulting in increase in capacity— |

not exceeding 10 megawatts

| £6,000

exceeding 10 megawatts but not exceeding 100 megawatts

| £18,000

exceeding 100 megawatts but not exceeding 200 megawatts

| £24,000

exceeding 200 megawatts but not exceeding 500 megawatts

| £36,000

exceeding 500 megawatts

| £60,000

6.

Extension of a nuclear generating station by retrofitting of emission control equipment | £6,000

7.

Any other extension of a generating station | £1,200

8.

Operation only or change to manner of operation of a generating station | £1,200