The Landfill (Scotland) Regulations 2003 (revoked), 10
Conditions to be included in landfill permits
Changed on 1 Nov 2025
(1) A landfill permit shall include conditions specifying the list of defined types, and the total quantity, of waste authorised to be deposited in the landfill.
(2) A landfill permit shall also include appropriate conditions–
(a) specifying requirements for–
(i) preparations for the landfill, and the carrying out of, landfilling operations;
(ii) monitoring and control procedures, including contingency plans and indicator parameters as set out in paragraph 4 of Schedule 4;
(b) ensuring that the financial provision or its equivalent required by regulation 18(4)(b) of the 2012 Regulations is maintained until the permit is surrendered in accordance with those Regulations;
(c) ensuring that the landfill is operated in such a manner that the necessary measures are taken to prevent accidents and to limit their consequences; and
(d) requiring the operator to report to SEPA, at such period as SEPA may require, and in any event annually–
(i) the types and quantities of waste disposed of; and
(ii) the results of the monitoring programme required by regulations 16 and 17.
(3) A landfill permit shall also include–
(a) appropriate conditions for ensuring compliance with the requirements of the following provisions of these Regulations–
(i) Schedule 3 (general requirements for all landfills);
(ii) regulation 11 (prohibition of acceptance of certain wastes at landfills);
(iii) regulation 12 (waste which may be accepted in the different classes of landfill);
(iv) regulation 13 (costs of disposal of waste in landfills);
(v) regulation 14 (waste acceptance procedures);
(vi) regulation 15 (initial site inspections by SEPA);
(vii) regulation 16 (control and monitoring of operational landfill sites); and
(viii) regulation 17 (closure and after care procedures for landfills); and
(aa) …
(b) such other conditions as appear appropriate to SEPA, including in particular conditions giving effect to–
(i) any requirement imposed by assimilated law or national legislation; and
(ii) in the case of landfills falling within paragraph (a) of Part A of Section 5.2 of Part 1 of Schedule 1 to the 2012 Regulations, the principle that energy should be used efficiently.
(4) The provisions of these Regulations mentioned in paragraph (3)(a) above impose obligations directly on an operator of a landfill (rather than through the conditions of a landfill permit) only to the extent specified in paragraph 3 of Schedule 5.…
- 1 Nov 2025 – todayin force
- 1 Jan 2024 – 1 Nov 2025earlier wording
- 31 Dec 2020 – 1 Jan 2024earlier wording
- 1 Aug 2013 – 31 Dec 2020earlier wording
- 7 Jan 2013 – 1 Aug 2013earlier wording
- 22 Apr 2011 – 7 Jan 2013earlier wording
- 10 Apr 2003 – 22 Apr 2011earlier wording