Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capa…, 33

Minimum interruption lead times

In forcesince 31 Dec 2020
1.

Transmission system operators must—

(a)

decide minimum interruption lead times jointly with adjacent TSOs that are transmission system operators; and

(b)

endeavour to decide minimum interruption lead times jointly with adjacent TSOs that are non-UK TSOs.

2.

The default minimum interruption lead time for a given gas hour shall be 45 minutes after the start of the re-nomination cycle for that gas hour. Where a transmission system operator and an adjacent TSO wish to shorten the lead time for interruptions, any related agreement entered into between the transmission system operators shall be subject to competent national regulatory authority approval.

Changed on 31 Dec 2020

1. Interruptible capacities shall have Transmission system operators must— (a) decide minimum interruption lead times, which shall be decided jointly by adjacent jointly with adjacent TSOs that are transmission system operators; and (b) endeavour to decide minimum interruption lead times jointly with adjacent TSOs that are non-UK TSOs. 2. The default minimum interruption lead time for a given gas hour shall be 45 minutes after the start of the re-nomination cycle for that gas hour. Where twoa transmission system operators operator and an adjacent TSO wish to shorten the lead time for interruptions, any related agreement entered into between the transmission system operators shall be subject to competent national regulatory authority approval.

  1. 31 Dec 2020 – todayin force
  2. 16 Mar 2017 – 31 Dec 2020earlier wording