The … transmission system operator shall organise stakeholder involvement regarding the implementation of this Regulation. Such involvement shall include regular meetings with stakeholders to identify problems and propose improvements related to the requirements of this Regulation.
Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on…, 53
Stakeholder involvement
In forcesince 1 Oct 2024
Changed on 1 Oct 2024
The national electricity … transmission system operator shall organise stakeholder involvement regarding the implementation of this Regulation. Such involvement shall include regular meetings with stakeholders to identify problems and propose improvements related to the requirements of this Regulation.
- 1 Oct 2024 – todayin force
- 31 Dec 2020 – 1 Oct 2024earlier wording
- 24 Nov 2017 – 31 Dec 2020earlier wording