Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on re…, 82

Register of derogations from the requirements of this Regulation

In forcesince 31 Dec 2020
1.

The regulatory authority must maintain a register of all derogations it has granted or refused.

2.

The register shall contain, in particular:

(a)

the requirement or requirements for which the derogation is granted or refused;

(b)

the content of the derogation;

(c)

the reasons for granting or refusing the derogation;

(d)

the consequences resulting from granting the derogation.

Changed on 31 Dec 2020

1. Regulatory authorities shall The regulatory authority must maintain a register of all derogations they haveit has granted or refused and shall provide the Agency with an updated and consolidated register at least once every six months, a copy of which shall be given to ENTSO for Electricity.

  1. 31 Dec 2020 – todayin force
  2. 26 Aug 2016 – 31 Dec 2020earlier wording