CCA 2009, s. 2
The interim targets
Climate Change (Emissions Reduction Targets) (Scotland) Act 201934Law
For section 2 of the 2009 Act, and the italic cross heading immediately preceding it, substitute— The interim targets The interim targets 2 (1) The Scottish Ministers must ensure that the net Scottish emissions account for the …
… as defined in section A1(1) of the Climate Change (Scotland) Act 2009 (asp 12); (b) the interim targets, as defined in section 2 of that Act; (c) a target in, or set under, section 1 or 2 of the Climate Change Act (Northern Ireland) …
Climate Change (Emissions Reduction Targets) (Scotland) Act 20242Law
(1) The Climate Change (Scotland) Act 2009 is modified as follows. (2) Section 2, and the italic cross heading immediately preceding it, are repealed. (3) Section 2A is repealed. (4) In section 2C— (a) in subsection (3)— (i) for …
The Forestry Commissioners (Climate Change Functions) (Scotland) Order 2012Law
… that Act, the Scottish Ministers consider it expedient to make this Order in order to comply with their duties under sections 1, 2(1) and 3(1)(b) of that Act. In accordance with section 96(4) of that Act, a draft of the Order has been laid …
The Climate Change (Scotland) Act 2009 (Interim Target) Amendment Regulations 20232Law
In section 2(1)(a) of the Climate Change (Scotland) Act 2009 (the interim targets), for “56%” substitute “48.5%”.
Changed on 23 Nov 2024
(1) The Scottish Ministers must ensure that the net Scottish emissions account for the year—
(a) 2020 is at least 48.5% lower than the baseline,
(b) 2030 is at least 75% lower than the baseline, and
(c) 2040 is at least 90% lower than the baseline.
(2) In this Act, each target set out in subsection (1) is known as an “interim target”.…
- 23 Nov 2024 – todayin force
- 31 May 2023 – 23 Nov 2024earlier wording
- 23 Mar 2020 – 31 May 2023earlier wording
- 22 Apr 2011 – 23 Mar 2020earlier wording
- 31 Oct 2009 – 22 Apr 2011earlier wording