Notation: M = mandatory; Miap = mandatory if applicable; V = voluntary.
Notes:
[Member States shall complete this field if expected new annual end-use energy savings are stable. If the new annual end-use energy savings are expected to change over time MS shall complete the fields per year.] [Member States shall specify the sectors (residential; services; industry; transport; other(s)) taken into account to calculate the target(s) of the EEOS and to define obligated parties. If the sectors eligible for individual actions are different, it shall be specified in the next field.] [Member States shall specify here the eligible actions. If the list of measures is too long, Member States shall mention here the main eligibility criteria and provide the list as a separate file. Member States shall specify the lifetime values assumed for the different types or categories of actions using Table 4 in this Annex.] [In case obligated parties are allowed to count towards their obligation certified energy savings achieved by energy service providers or other third parties, Member States shall explain the eligibility criteria for these third parties and how it is ensured that the certification of energy savings follows an approval process that is clear and transparent.] [Member States shall specify if obligated parties can or shall fulfil their savings obligation, in whole or in part, as a contribution to an Energy Efficiency National Fund.] [Member States shall specify the methods used according to the typology defined in Annex V (1) to Directive 2012/27/EU: (a) deemed savings / (b) metered savings / (c) scaled savings / (d) surveyed savings. Member States shall explain in case another type of method is used.] [Member States shall add explanation, especially if a method different from the one presented in point 2(i) of Annex V to Directive 2012/27/EU and point 2(p) of Annex V to Directive (EU) 2023/1791 is used).] [Member States shall explain how the calculation methodology complies with points (a) to (c) of Annex V (2) to Directive 2012/27/EU and points (a) to (f) of Annex V(2) to Directive (EU) 2023/1791.] [Member States shall explain how such overlaps are taken into account in the savings calculations, for example interactions between insulation of walls and replacement of heating systems. Member States shall also explain how the M&V system prevents the same individual action to be reported by several obligated parties (avoiding double counting within the EEOS).] [Member States shall explain how verification of statistically representative samples of actions is ensured, and specify the criteria used to define and select representative samples.]
PaM Number | M |
Source(s) of information (including the reference of the related law or other legal text(s)) | M |
Expected savings for 2021-2030 and duration of the obligation period(s) (points 5(d) and 5(e) of Annex V to Directive 2012/27/EU or points 5(a) and 5(j) of Annex V to Directive (EU) 2023/1791) |
Expected cumulative end-use energy savings for the period 2021-2030 (ktoe) | M |
Expected new annual end-use energy savings (ktoe/year) | Miap |
2021 | Miap |
2022 | Miap |
2023 | Miap |
2024 | Miap |
2025 | Miap |
2026 | Miap |
2027 | Miap |
2028 | Miap |
2029 | Miap |
2030 | Miap |
Duration of the obligation period(s) | M |
Key design features |
Obligated parties (point 5(b) of Annex V to Directive 2012/27/EU and point 5(c) of Annex V to Directive (EU) 2023/1791) | M |
Target sectors (point 5(c) of Annex V to Directive 2012/27/EU and point 5(d) of Annex V to Directive (EU) 2023/1791) | M |
Sectors where individual actions are eligible to the EEOS (if different from the target sectors listed above) (point 5(c) of Annex V to Directive 2012/27/EU and point 5(d) of Annex V to Directive (EU) 2023/1791) | M |
Individual actions eligible to the EEOS (point 5(f) of Annex V to Directive 2012/27/EU and point 5(l) of Annex V to Directive (EU) 2023/1791) and corresponding lifetimes (points 2(i) and 5(h) of Annex V to Directive 2012/27/EU and point 5(n) of Annex V to Directive (EU) 2023/1791) | M |
Information on the application of the following EED provisions: |
Energy poverty indicators applied | Miap |
Arithmetic share established | Miap |
Share of the required amount of cumulative end-use energy savings achieved among people affected by energy poverty, vulnerable customers, people in low-income households and, where applicable, people living in social housing | Miap |
Savings achieved by energy service providers or other third parties (Article 7a(6), point (a) of Directive 2012/27/EU and Article 9(11), point (a) of Directive (EU) 2023/1791 | Miap |
Rules about banking and borrowing (Article 7a(6), point (b), of Directive 2012/27/EU and Article 9(11), point (b), of Directive (EU) 2023/1791) | Miap |
Possibilities for trading of energy savings (where relevant) | Miap |
Interactions with a National Energy Efficiency Fund in accordance with Article 30(12) of Directive (EU) 2023/1791 | Miap |
General information about the calculation methodology |
Calculation method(s) used (point 1 of Annex V, to Directive 2012/27/EU and point 1 of Annex V to Directive (EU) 2023/1791) | M |
Metric(s) used to express the energy savings (primary or final energy savings) (Article 7a(4), and point 3(d) of Annex V to Directive 2012/27/EU` and point 3(d) of Annex V to Directive (EU) 2023/1791) | M |
How are lifetimes (and possible changes in savings over time) taken into account in savings calculations (points 2(i) and 5(h) of Annex V to Directive 2012/27/EU and points 2(p) and 5(n) of Annex V to Directive (EU) 2023/1791) | M |
Other sources of information or references (e.g. studies, evaluation reports) where more explanations and details about the savings calculations can be found | V |
Additionality and materiality (requirements related to points 2 and 5(g) of Annex V to Directive 2012/27/EU and points 2 and 5(m) of Annex V to Directive (EU) 2023/1791) |
Description of the calculation methodology; including how additionality is taken into account in the calculation methodology (point 2(a) of Annex V to Directive 2012/27/EU and point 2(b) of Annex V to Directive (EU) 2023/1791) | M |
Does the EEOS promote early replacements? If so, how is it taken into account in the calculation of the savings? (point 2(f) of Annex V to Directive 2012/27/EU and point 2(m) of Annex V to Directive (EU) 2023/1791) | M |
Benchmarks used for deemed and scaled savings (in case deemed or scaled savings are used) (point 1(c) of Annex V to Directive 2012/27/EU and point 1(c) of Annex V to Directive (EU) 2023/1791) | M |
How is materiality of savings ensured? (point 3(h) of Annex V to Directive 2012/27/EU and point 3(h) of Annex V to Directive (EU) 2023/1791) | M |
Possible overlaps (between policy measures and between individual actions) and double counting |
Possible overlaps between individual actions eligible to the EEOS | Miap |
Possible overlaps between the EEOS and alternative measure(s) reported according to Article 7 of Directive 2012/27/EU and Article 8 of Directive (EU) 2023/1791 | Miap |
How are possible overlaps (between the EEOS and alternative measures) addressed to avoid any double counting of energy savings? (point 3(g) of Annex V to Directive 2012/27/EU and point 3(g) of Annex V to Directive (EU) 2023/1791) | M |
Climatic variations (where relevant) (points 2(h) and 5(i) of Annex V to Directive 2012/27/EU and points 2(o) and 5(c) of Annex V to Directive (EU) 2023/1791) |
Are there climatic variations between regions? And can they affect the actions eligible to the EEOS? | Miap |
How are climatic variations addressed in savings calculations where relevant? | Miap |
Monitoring and verification (M&V) of savings (point 5(j) of Annex V to Directive 2012/27/EU and point 5(p) of Annex V to Directive (EU) 2023/1791) |
Brief description of the monitoring & verification system and of the process of verification, including on the methods used | M |
Issues identified and how they were addressed | Miap |
Authorities responsible for the M&V of the EEOS | M |
Independence of the M&V from obligated parties (Article 7a(5) of Directive 2012/27/EU and Article 9(9) of Directive (EU) 2023/1791) | M |
Verification of statistically representative samples (Article 7a(5) of Directive 2012/27/EU and Article 9(9) of Directive (EU) 2023/1791) | M |
Reporting obligations for obligated parties (savings achieved by each obligated party, or each sub-category of obligated party, and in total under the scheme) | M |
Publication of energy savings achieved each year under the EEOS (Article 7a (7) of Directive 2012/27/EU and Article 9(12) of Directive (EU) 2023/1791) | M |
Penalties applied in case of non-compliance (and related references, including the law or other legal texts setting the penalties and related conditions) | M |
Provision(s) in case the progress of the EEOS is not satisfactory (point 3(f) of Annex V to Directive 2012/27/EU and point 3(f) of Annex V to Directive (EU) 2023/1791) | M |
Information about quality standards (point 2(g) of Annex V to Directive 2012/27/EU and point 2(n) of Annex V to Directive (EU) 2023/1791) |
How are quality standards (for products, services and installation of measures) promoted or required by the EEOS? | Miap |
Complementary information or explanations |
Mention here any other information or explanation that can be useful for experience sharing | V |
Notation: M = mandatory; Miap = mandatory if applicable; V = voluntary.
Notes:
[Member States shall complete this field if expected new annual end-use energy savings are stable. If the new annual end-use energy savings are expected to change over time MS shall complete the fields per year.] [Member States shall indicate here the periods or dates used to define intermediate objectives to enable reviewing the progress of the alternative measure.] [Member States shall specify the sectors (residential; services; industry; transport; other(s)) taken into account.] [Member States shall specify the categories of individual actions that can receive financial incentives or other types of support from the alternative measure, or that are promoted by the alternative measure through regulations, information or any type of policy instrument. If the list of measures is too long, Member States shall mention here the main eligibility criteria and provide the list as a separate file. Member States shall specify the lifetime values assumed for the different types or categories of actions using Table 4 in this Annex.] [Member States shall specify the methods used according to the typology defined in Annex V (1) to Directive 2012/27/EU: (a) deemed savings / (b) metered savings / (c) scaled savings / (d) surveyed savings. Member States shall explain in case another type of method is used.] [Member States shall add explanation, especially if a method different from the one presented in point 2(i) of Annex V to Directive 2012/27/EU and point 2(p) of Annex V to Directive (EU) 2023/1791 is used).] [Member States shall explain how the calculation methodology complies with points (a) to (c) of Annex V (2) to Directive 2012/27/EU and points (a) to (f) of Annex V(2) to Directive (EU) 2023/1791.] [Member States shall explain how such overlaps are taken into account in the savings calculations, for example interactions between insulation of walls and replacement of heating systems.] [Member States shall explain how verification of statistically representative samples of actions is ensured, and specify the criteria used to define and select representative samples.]
PaM Number | M |
Source(s) of information (including the reference of the related law or other legal text(s)) | M |
Budget planned or estimated, including the corresponding implementation period(s) | V |
Expected savings for 2021-2030 and duration of the obligation period(s) (points 5(d) and 5(e) of Annex V to Directive 2012/27/EU and points 5(e) and 5(j) of Annex V to Directive (EU) 2023/1791) |
Expected cumulative end-use energy savings for the period 2021-2030 (ktoe) | M |
Expected new annual end-use energy savings (ktoe/year) | Miap |
2021 | Miap |
2022 | Miap |
2023 | Miap |
2024 | Miap |
2025 | Miap |
2026 | Miap |
2027 | Miap |
2028 | Miap |
2029 | Miap |
2030 | Miap |
Intermediate period(s), where relevant | Miap |
Key design features |
Implementing public authorities, participating or entrusted parties and their responsibilities for implementing the policy measure (points 3(b) and 5(b) of Annex V to Directive 2012/27/EU and points 3(b) and 5(c) of Annex V to Directive (EU) 2023/1791) | M |
Target sectors (point 5(c) of Annex V to Directive 2012/27/EU and point 5(d) of Annex V to Directive (EU) 2023/1791) | M |
Individual actions eligible to the alternative measure (point 5(f) of Annex V to Directive 2012/27/EU and point 5(l) of Annex V to Directive (EU) 2023/1791) and corresponding lifetimes (points 2(i) and 5(h) of Annex V to Directive 2012/27/EU and point 5(n) of Annex V to Directive (EU) 2023/1791) | M |
Specific policy measures or individual actions targeting energy poverty (where applicable) | Miap |
General information about the calculation methodology |
Measurement method(s) used (point 1 of Annex V to Directive 2012/27/EU and point 1 of Annex V to Directive (EU) 2023/1791) | M |
Metric(s) used to express the energy savings (primary or final energy savings) (point 3(d) of Annex V to Directive 2012/27/EU and point 3(d) of Annex V to Directive (EU) 2023/1791) | M |
How are lifetimes (and possible changes in savings over time) taken into account in savings calculations (points 2(i) and 5(h) of Annex V to Directive 2012/27/EU and point 5(n) of Annex V to Directive (EU) 2023/1791) | M |
Other sources of information or references (e.g. studies, evaluation reports) where more explanations and details about the savings calculations can be found | V |
Additionality and materiality (requirements related to points 2 and 5(g) of Annex V to Directive 2012/27/EU and points 2 and 5(m) of Annex V to Directive (EU) 2023/1791) |
Description of the calculation methodology; including how additionality is taken into account in the calculation methodology (point 2(a) of Annex V to Directive 2012/27/EU and point 2(b) of Annex V to Directive (EU) 2023/1791) | M |
Does the policy measure promote early replacements? If so, how is it taken into account in the calculation of the savings? (point 2(f) of Annex V to Directive 2012/27/EU and point 2(m) of Annex V to Directive (EU) 2023/1791) | M |
Benchmarks used for deemed and scaled savings (in case deemed or scaled savings are used) (point 1(c) of Annex V to Directive 2012/27/EU and point 1(c) of Annex V to Directive (EU) 2023/1791) | M |
How is materiality of savings ensured? (point 3(h) of Annex V to Directive 2012/27/EU and point 3(h) of Annex V to Directive (EU) 2023/1791) | M |
Possible overlaps (between policy measures and between individual actions) and double counting |
Possible overlaps between individual actions eligible to the policy measure | Miap |
Possible overlaps between the EEOS (if any) and alternative measure(s) reported according to Article 7 of Directive 2012/27/EU | Miap |
How are possible overlaps (between the EEOS, if any, and alternative measures) addressed to avoid any double counting of energy savings? (point 3(g) of Annex V to Directive 2012/27/EU and point 3(g) of Annex V to Directive (EU) 2023/1791) | M |
Climatic variations (where relevant) (points 2(h) and 5(i) of Annex V to Directive 2012/27/EU and points 2(o) and 5(c) of Annex V to Directive (EU) 2023/1791) |
Are there climatic variations between regions? And can they affect the actions eligible to the policy measure? | Miap |
How are climatic variations addressed in savings calculations where relevant? | Miap |
Monitoring and verification (M&V) of savings (point 5(j) of Annex V to Directive 2012/27/EU and point 5(p) of Annex V to Directive (EU) 2023/1791) |
Brief description of the monitoring & verification system and of the process of verification, including methods used | M |
Issues identified and how they were addressed | Miap |
Authorities responsible for the M&V of the policy measure | M |
Independence of the M&V from the participating or entrusted parties (Article 7b(2) of Directive 2012/27/EU and Article 10(2) of Directive (EU) 2023/1791) | M |
Verification of statistically representative samples (Article 7b(2) of Directive 2012/27/EU and Article 10(2) of Directive (EU) 2023/1791) | M |
Publication of energy savings achieved each year under the policy measure (point 3(e) of Annex V to Directive 2012/27/EU and point 3(e) of Annex V to Directive (EU) 2023/1791) | M |
Penalties applied in case of non-compliance (and related references, including the law or other legal texts setting the penalties and related conditions) | M |
Provision(s) in case the progress of the policy measure is not satisfactory (point 3(f) of Annex V to Directive 2012/27/EU and point 3(f) of Annex V to Directive (EU) 2023/1791) | M |
Information about quality standards (point 2(g) of Annex V to Directive 2012/27/EU and point 2(n) of Annex V to Directive (EU) 2023/1791) |
How are quality standards (for products, services and installation of measures) promoted or required by the policy measure? | Miap |
Complementary information or explanations |
Any other information or explanation that can be useful for experience sharing | V |
Notation: M = mandatory; Miap = mandatory if applicable; V = voluntary
Notes:
[Member States shall specify the sectors (residential; services; industry; transport; other(s)) taken into account.] [Member States shall complete this field if expected new annual end-use energy savings are stable. If the new annual end-use energy savings are expected to change over time MS shall complete the fields per year.] [Member States shall explain the model used to calculate the savings, if short-term and/or long-term elasticities are taken into account and why, the variables taken into account in the model and how they were selected.] [Member States shall explain the method for analysing the effects on energy consumption with and without the taxation measure (counterfactual); How the counterfactual is defined, and how it is ensured that at least the minimum EU levels of taxation are taken into account.] [When relevant, Member States shall explain how the short-term elasticities are defined, ensuring that they represent the responsiveness of energy demand to price changes. Member States shall mention the data sources to be used to define the elasticities.] [When relevant, Member States shall explain how the long-term elasticities are defined, ensuring that they represent the responsiveness of energy demand to price changes. Member States shall mention the data sources to be used to define the elasticities.] [Member States shall explain how the calculation methodology ensures that only savings from individual actions implemented after 31 December 2020 and before 31 December 2030 can be taken into account.] [Member States shall explain how the independence of the evaluator(s) of the energy savings from the taxation measure is ensured.]
PaM Number | M |
Duration of taxation measure (point 5(k)(iv) of Annex V to Directive 2012/27/EU and point 5(q)(iv) of Annex V to Directive (EU) 2023/1791) | M |
Implementing public authority (point 5(k)(ii) of Annex V to Directive 2012/27/EU and point 5(q)(ii) of Annex V to Directive (EU) 2023/1791) | M |
Target sectors and segment of taxpayers (point 5(k)(i) of Annex V to Directive 2012/27/EU and point 5(q)(i) of Annex V to Directive (EU) 2023/1791) | M |
Source(s) of information (including the reference of the related law or other legal text(s)) | M |
Expected savings for 2021-2030 and duration of the obligation period(s) (points 5(d) and 5(e) of Annex V to Directive 2012/27/EU or points 5(e) and 5(j) of Annex V to Directive (EU) 2023/1791) |
Expected cumulative end-use energy savings for the period 2021-2030 (ktoe) | M |
Expected new annual end-use energy savings (ktoe/year) | Miap |
2021 | Miap |
2022 | Miap |
2023 | Miap |
2024 | Miap |
2025 | Miap |
2026 | Miap |
2027 | Miap |
2028 | Miap |
2029 | Miap |
2030 | Miap |
Complementary explanations (when relevant) | V |
General information about the calculation methodology |
Calculation method(s) used | M |
Approach to calculating savings (point 4(a) of Annex V to Directive 2012/27/EU and point 4(a) of Annex V to Directive (EU) 2023/1791) | M |
Elasticities (short-term) (point 4(b) of Annex V to Directive 2012/27/EU and point 4(b) of Annex V to Directive (EU) 2023/1791) | Miap |
Elasticities (long-term) (point 4(b) of Annex V to Directive 2012/27/EU) | Miap |
How lifetimes are addressed in savings calculations (point 2(i) of Annex V to Directive 2012/27/EU and point 2(n) of Annex V to Directive (EU) 2023/1791) | M |
How is double counting with other policy measure(s) avoided? (point 4(c) of Annex V to Directive 2012/27/EU and point 4(c) of Annex V to Directive (EU) 2023/1791) | M |
Independence from the implementing public authority | M |
Complementary explanations and source(s) of information | V |
Notation: Miap = mandatory if applicable
Eligible action | End-use sector | Assumed lifetime value (in years) | Assumptions about possible changes in the energy savings over time | Source or method used to estimate the lifetime and related assumptions
Miap | Miap | Miap | Miap | Miap
Action 1 | | | |
Action 2 | | | |
Action 3 | | | |