According to the documents submitted by Greece, the upgrade of the ETCS equipment to meet latest requirements (ETCS Baseline 4) would delay the use of ETCS aboard those vehicles from late 2026 to 2030. Complying with paragraph (1) of point 7.4.2.4.1 of Annex I to Implementing Regulation (EU) 2023/1695 would entail an additional cost of approximately EUR 59000000, due to the costs of the upgrade to the currently required version of specifications and due to the revenue lost if vehicles were to be immobilised until 2030. These additional costs would compromise the economic viability of the project. Additionally, the four years delay in the use of ETCS would delay the expected significant improvement of the current level of safety of the Greek rail network.