When choosing to assess the auction’s sustainability contribution referred to in Article 26(1), point (b), of Regulation (EU) 2024/1735 by means of energy system integration criteria, the relevant authorities shall take into account the contribution of the participating projects to addressing system needs resulting from their operation, based on temporal flexibility, locational impact and connections across energy carriers, under the conditions laid down in paragraphs 2, 3 and 4.
The participating project’s temporal flexibility shall be assessed with regard to the solutions proposed, either as new investments or procured through third parties, in particular in the form of a combination of several renewable generation technologies, a combination of generation assets and electricity storage assets, or a combination of generation assets and demand assets or solutions. Unless duly justified, this assessment shall not exclude any technology that can contribute to address the identified system needs.
The participating project’s locational impact on system needs shall be assessed with regard to the combination of their relevant features, including their temporal generation profile or their generation capacity, and the selection of the site and of the grid connection point, while taking into account network planning.
The participating project’s ability to creating connections across energy carriers shall be assessed with regard to their capacity to transfer renewable energy from one energy carrier to another, and in particular whether they include a combination of generation assets and energy conversion assets.