Spain and Portugal made every effort to align with the core network deadline of 2030, as substantiated by the significant advances made on the Évora-Merida and Merida-Plasencia sections. Spain is also committed to making every effort to finalise the new high-speed line section between Talayuela and Madrid by 2030. However, because of technical and financial constraints faced by Portugal, the high-speed rail connection between Lisbon and Madrid will not be finalised before the end of 2030. It should be fully concluded before the end of 2034.
Recital 10, Decision_act (EU) 2025/2198
In forcesince 30 Oct 2025