France and Italy have already carried out significant actions such as studies and infrastructure works. Those actions include the ongoing construction of the base tunnel in both countries (as of 31 October 2024), where 38,6 km of galleries have been excavated, out of which 14,7 km of the base tunnel), the planning of access lines on the Italian territory, the planning of the modernisation of the conventional rail line Ambérieu – Saint-Jean-de-Maurienne as from 2027 with a dedicated budget of EUR 700 million, and the ongoing modernisation of the conventional rail line between Bussoleno-Avigliana. Regarding the French new railway lines, a decree of 13 August 2013 [Journal Officiel de la République Française no. 197 of 25 August 2013.] declared the works to be in the public interest, the detailed railway alignment was approved. The avant-projet détaillé (APD) studies, co-financed by the Commission, France and the French regional authorities will be launched in 2025.
Recital 11, Decision_act (EU) 2025/1715
In forcesince 30 Jul 2025