Art. 5 Decision_act (EU) 2025/1332

Governance and reporting

In forcesince 9 Jul 2025
1.

The European Coordinator for the North Sea-Baltic European Transport Corridor, representatives of the Commission and nominated representatives of Poland and Finland shall be invited to participate as observers in the meetings of the Supervisory Board of RB Rail AS. RB Rail AS may also decide to invite the European Coordinator or the Commission to strategic meetings of the project partners.

2.

The Rail Baltica Task Force shall meet upon invitation of the European Coordinator for the North Sea – Baltic European Transport Corridor at least twice per year. It shall be consulted about strategic decisions for the project. The European Coordinator of the North Sea – Baltic corridor shall keep the European Coordinator of the Baltic Sea – Black Sea – Aegean Sea informed about significant developments related to the Rail Baltica project and relevant for the two corridors.

3.

After consulting Estonia, Latvia, Lithuania and Poland, RB Rail AS shall provide updated information to the European Coordinator for the North Sea – Baltic corridor in writing at least once per year about the progress in implementing the actions referred to in Article 2 and shall where relevant notify any delay encountered, specifying the reasons for the delay and indicating the corrective measures taken.

4.

If force majeure has an impact on the implementation programme and its financing, the project partners and the European Coordinator for the North Sea – Baltic corridor shall consult each other to define corrective measures.