The multimodal freight terminals of the trans-European transport network are terminals that are open to all operators and users in a non-discriminatory way and are:
located in or adjacent to the maritime ports of the trans-European transport network, as listed in Annex II;
located in or adjacent to the inland ports of the trans-European transport network, as listed in Annex II;
located in the airports of the trans-European transport network, as listed in Annex II; or
classified as rail road terminals or terminals along the inland waterways of the trans-European transport network, as listed in Annex II.
Member States shall make all possible efforts to ensure that there is sufficient multimodal freight terminal capacity serving the trans-European transport network, taking into account current and future traffic flows, in particular flows serving urban nodes, industrial centres, ports and logistics hubs.
By 19 July 2027, Member States shall conduct a market and prospective analysis on multimodal freight terminals on their territory. This analysis shall at least:
examine the current and the future traffic flows of freight, per transport mode;
identify the existing multimodal freight terminals of the trans-European transport network on their territory, and assess the need for new multimodal freight terminals or additional transhipment capacity in existing terminals; and
analyse how to ensure adequate distribution of multimodal freight terminals with adequate transhipment capacity in order to meet the needs identified in point (b), this shall take into account the terminals located in border areas of neighbouring Member States.
Member States shall consult shippers, transport, logistics operators, as well as other relevant stakeholders which operate on their territory. They shall take into account the results of the consultation in their analysis.
Member States shall notify the results of the analysis to the Commission without delay.
Where the analysis referred to in paragraph 3 identifies the need for new multimodal freight terminals or additional transhipment capacity in existing terminals, Member States shall elaborate an action plan for the development of a multimodal freight terminal network, including locations where such needs have been identified.
The action plan shall be notified to the Commission no later than 12 months after finalising the analysis referred to in paragraph 3.
On the basis of that action plan, Member States shall notify to the Commission a list of rail road terminals and terminals along inland waterways which they propose to add to Annexes I and II.
In order to be part of the trans-European transport network and to be listed in Annex II, a rail road terminal or a terminal along inland waterways shall meet at least one of the following conditions:
its annual transhipment of freight exceeds, for non-bulk cargo, 800000 tonnes or, for bulk cargo, 0,1 % of the corresponding total annual cargo volume handled in all maritime ports of the Union;
it is the main rail road terminal designated by the Member State for a NUTS 2 region, where there is no rail road terminal complying with point (a) in that NUTS 2 region;
it is proposed to be added in Annexes I and II by the Member State in accordance with paragraph 4 of this Article.