1.

Within 7 months after submitting the first draft Union-wide cybersecurity risk assessment report pursuant to Article 19(4), the TSOs, with the assistance of the ENTSO for Electricity, and in cooperation with the EU DSO entity and in consultation with ENISA, shall develop a proposal for a matrix to map the controls set out in Article 28(1), points (a) and (b) against selected European and international standards as well as relevant technical specifications (‘the mapping matrix’). The ENTSO for Electricity and the EU DSO entity shall document the equivalence of the different controls with the controls set out in Article 28(1), points (a) and (b).

2.

The competent authorities may provide to the ENTSO for Electricity and the EU DSO entity a mapping of the controls set out in Article 28(1), points (a) and (b) with a reference to the related national legislative or regulatory frameworks, including relevant national standards of Member States pursuant to Article 25 of Directive (EU) 2022/2555. If the competent authority of a Member State provides such a mapping, the ENTSO for Electricity and the EU DSO entity shall integrate this national mapping into the mapping-matrix.

3.

Within 6 months after drawing up each regional cybersecurity risk assessment report pursuant to Article 21(2), the TSOs, with the assistance of the ENTSO for Electricity, and in cooperation with the EU DSO Entity and in consultation with ENISA, shall propose an amendment to the competent authority for mapping matrix. The proposal will be done in accordance with Article 8(10) and will take into account the risks identified in the regional risk assessment.