The expected improvement in cost-efficiency for RP4 should be calculated starting from the Union-wide baseline value for the DUC, which is derived by dividing the baseline value for the Union-wide determined costs with the STATFOR base traffic forecast expressed in service units for the year 2024. The baseline value for Union-wide determined costs should be estimated by using the latest available data on the actual costs of air navigation service provision in RP3, as adjusted on the basis of the preliminary cost data for year 2024 received from Member States in June 2023 and estimates on the level of costs for year 2024 resulting from PRB analysis. Account should be taken of the forecasted traffic variations during the remaining time period of RP3 and their relation to costs.
Recital 24, Decision_act (EU) 2024/1688
In forcesince 12 Jun 2024