Recital 8, Decision_act (EU) 2024/378

In forcesince 25 Jan 2024

Because of the absence of the relevant ETCS/ERTMS equipment on board, the Stadler E6000 vehicles object of this request cannot currently operate on that line. Retrofitting those vehicles to install the ERTMS on board, would compromise the viability of the project due to the additional costs related to the expected delays of several months in the entry in operation and the lack of availability of the locomotives. Also, at this stage retrofitting would bring limited benefits because of the limited length of the track where ERTMS can be used and the additional complexity and costs of having two onboard signalling systems in use. The Spanish national implementation plan to develop ERTMS foresees the installation of ERTMS Level 2 (Baseline 3) by 2030 in the sections adjacent to the 50 km of the Puerto de Pajares section (L084/984).