Contracting authorities and contracting entities may on an exceptional basis decide not to apply an IPI measure with respect to a public procurement procedure where:
only tenders from economic operators originating in a third country subject to an IPI measure meet the tender requirements; or
the decision not to apply the IPI measure is justified for overriding reasons relating to the public interest, such as public health or protection of the environment.
Where a contracting authority or contracting entity decides not to apply an IPI measure, it shall provide the following information to the Commission, in a manner to be decided by the respective Member State and no later than thirty days after the award of the contract:
the name and contact details of the contracting authority or contracting entity;
a description of the object of the contract;
information on the origin of the economic operators;
the ground on which the decision not to apply the IPI measure is based, and a detailed justification for the application of the exception;
where appropriate, any other information deemed useful by the contracting authority or contracting entity.
The Commission may ask the Member States concerned for additional information.