To directly enable the achievement of the EU 2030 renewable energy target, the cross-border projects should always include a renewables generation facility as an integral part of the project. Additional components of the project that indirectly enable the achievement of the EU 2030 renewable energy target and the cost-effective deployment of renewable energy by contributing to the effective integration of the renewables generation can be eligible, however not as stand-alone projects, but as integral part of the cross-border project which is deployed in addition to the renewables generation. Such additional components can be cross-border transmission grid, thermal storage, battery storage, compressed air and liquid air storage, pumped hydro and electrolysis of water coupled with hydrogen storage. Eligible action is not limited to the electricity sector and can cover other energy carriers and potential sector coupling, for example with heating and cooling, power to gas, storage and transport.
Recital 14, Regulation (EU) 2022/342
In forcesince 21 Dec 2021