(23)

The lower number of forecasted service units for the 2022, 2023 and 2024 calendar years is partly offset by Lithuania through a reduction of determined costs. The Commission notes that Lithuania proposes to revise downwards the determined costs in real terms in 2017 prices for each of those years, as laid down in the following table:

En route charging zone of Lithuania | 2022 | 2023 | 2024

Initial determined costs in real terms in 2017 prices (included in the performance plan) | 22,5 M EUR | 25,1 M EUR | 25,3 M EUR

Intended revised determined costs in real terms in 2017 prices | 18,2 M EUR | 19,5 M EUR | 20,0 M EUR

Difference | -19,0 % | -22,2 % | -20,8 %