A new ITER project baseline, which was prepared as part of the improvements in the management of the project, gained the support of the ITER Council in 2016 and 2017. It was subsequently used for estimating the funding needs of the Joint Undertaking. The updated schedule of the new baseline envisages that First Plasma will be achieved in December 2025 and full performance operation, using deuterium-tritium fuel, in 2035. That schedule does not include contingencies and therefore assumes that all major risks have to be mitigated.