In case of failure of the applicant to implement the project and in order to safeguard the legitimate expectations of Member States, it is appropriate that the Member States participating in a project which failed to be implemented by the applicant should be considered to have taken additional measures in accordance with Article 32(3) of Regulation (EU) 2018/1999 for an amount of energy calculated and accounted for separately by the Commission on the basis of the expected generation capacity, the financial contribution paid by that Member State, and the ceiling prices applicable to the call in which that Member State committed to participate, for the period during which the project would have given rise to statistical benefits according to Article 27(2). This should be without prejudice to the renewable energy target for the Union for 2030 of at least 32 % pursuant to Directive (EU) 2018/2001.
Recital 26, Regulation (EU) 2020/1294
In forcesince 15 Sep 2020