Every year the competent authority shall compare the average activity level of each sub-installation, determined in accordance with Article 4, with the historical activity level initially used to determine the free allocation. When the absolute value of the difference between the average activity level and the historical activity level of that sub-installation is more than 15 % of that historical activity level, the free allocation of allowances to that installation shall be adjusted. That adjustment shall apply as of the year following the two calendar years used for determining the average activity level and be made by increasing or decreasing the free allocation for the relevant sub-installation by the exact percentage change in the average activity level compared to the historical activity level initially used to determine the free allocation.
For heat benchmark sub-installations, fuel benchmark sub-installations and process emissions sub-installations the adjustment referred to in the first subparagraph shall be based on the average of the expected activity level. Adjustments for each of those sub-installations shall only be made if the absolute value of the adjustment is more than 15 %.
For the purpose of paragraph 1, second subparagraph, and where the value of the difference referred to in paragraph 1, first subparagraph, is exceeded, the operator shall attribute the relevant amounts of heat, fuel and process emissions to each relevant product in accordance with the methodology set out in Annex I, applying the same methods as for attributing data to sub-installations as set out in Section 3.2 of Annex VII to Delegated Regulation (EU) 2019/331. The operator shall describe the applied methodologies in the monitoring methodology plan as approved in accordance with Article 6 of that Regulation.
When an adjustment in accordance with paragraph 1 has been made, during an allocation period, further adjustments can only take place if the absolute value of the difference between the average activity level and the historical activity level of that sub-installation, exceeds the nearest 5 % interval, beyond the 15 % change, which caused the previous adjustment of free allocation to that installation, by increasing or decreasing the free allocation for the relevant sub-installation by the exact percentage change in the average activity level compared to the historical activity level initially used to determine the free allocation.
For heat benchmark sub-installations, fuel benchmark sub-installations and process emissions sub-installations the value of the difference referred to in the first subparagraph shall refer to the average of the expected activity level.
If the increase or decrease of the average activity level of a sub-installation no longer exceeds 15 % compared to the historical activity level initially used to determine the free allocation, the free allocation of allowances to that sub-installation shall be equal to the initial allocation determined by Article 16 or 18 of Delegated Regulation (EU) 2019/331, as of the year following the two calendar years used for determining the average activity level.
If a sub-installation has ceased operation, it shall not be entitled to the free allocation for the remainder of the calendar year following the day of cessation of operations, on a pro-rata basis, and the free allocation of that sub-installation shall be set to zero as of the year following the cessation of operations.
For new sub-installations and for new entrants, for the first three calendar years of operation the free allocation of emission allowances shall not be adjusted. For the first and second calendar years of operation, the free allocation of emission allowances shall be based on the activity level of each year respectively, for the third calendar year of operation the free allocation of emission allowances shall be based on the historical activity level used to determine free allocation.
The final annual amount of emission allowances allocated for free to an installation shall be the sum of emission allowances of all sub-installations calculated in accordance with Article 16 or 18, as applicable, of Delegated Regulation (EU) 2019/331.