Art. 10 Regulation (EU) 2019/943

Technical bidding limits

In forcesince 5 Jun 2019cited 16×
1.

There shall be neither a maximum nor a minimum limit to the wholesale electricity price. This provision shall apply, inter alia, to bidding and clearing in all timeframes and shall include balancing energy and imbalance prices, without prejudice to the technical price limits which may be applied in the balancing timeframe and in the day-ahead and intraday timeframes in accordance with paragraph 2.

2.

NEMOs may apply harmonised limits on maximum and minimum clearing prices for day-ahead and intraday timeframes. Those limits shall be sufficiently high so as not to unnecessarily restrict trade, shall be harmonised for the internal market and shall take into account the maximum value of lost load. NEMOs shall implement a transparent mechanism to adjust automatically the technical bidding limits in due time in the event that the set limits are expected to be reached. The adjusted higher limits shall remain applicable until further increases under that mechanism are required.

3.

Transmission system operators shall not take any measures for the purpose of changing wholesale prices.

4.

Regulatory authorities or, where a Member State has designated another competent authority for that purpose, such designated competent authorities, shall identify policies and measures applied within their territory that could contribute to indirectly restricting wholesale price formation, including limiting bids relating to the activation of balancing energy, capacity mechanisms, measures by the transmission system operators, measures intended to challenge market outcomes, or to prevent the abuse of dominant positions or inefficiently defined bidding zones.

5.

Where a regulatory authority or designated competent authority has identified a policy or measure which could serve to restrict wholesale price formation it shall take all appropriate actions to eliminate or, if not possible, to mitigate the impact of that policy or measure on bidding behaviour. Member States shall provide a report to the Commission by 5 January 2020 detailing the measures and actions they have taken or intend to take.

The 10 that are cited most themselves, of 16.

  • Regulation (EU) 2019/94215Law

    … цените да отразяват действителния недостиг, както се посочва в член 10, параграф 4 от Регламент (ЕС) 2019/943, и постиженията на …

  • Decision_act (EU) 2024/5601Lawamends

    … 1, litra a), b), e), k), o) og p), artikel 6, artikel 7, stk. 1, artikel 8, stk. 1 og 4, artikel 9, 10 og 11, artikel 20, stk. 3-8, artikel 21, stk. 7, artikel 22, stk. 2 og 3, og artikel 25, stk. 2-4 i forordning (EU) 2019/943 og artikel …

  • Regulation (EU) 2024/178985Law

    … цените да отразяват действителния недостиг, както се посочва в член 10, параграф 4 от Регламент (ЕС) 2019/943, и постиженията на …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 12 March 2025. PGI Spain, SL and Others v European Commission.Decision

    In support of their action, the applicants rely on five pleas in law, alleging (i) a misunderstanding by the Commission of the notified measure; (ii) errors in the assessment of the appropriateness and proportionality of the notified …

    12 Mar 2025 · 62022TJ0596

  • Opinion of Advocate General Rantos delivered on 29 September 2022. Bursa Română de Mărfuri SA v Autoritatea Naţională de Reglementare în domDecision

    Article 1(b) and (c) and Article 3 of that regulation, which BRM invokes on the ground that they require national regulatory authorities to promote competition between operators on the electricity markets, do not in themselves preclude the …

    29 Sep 2022 · 62021CC0394

  • Decision_act (EU) 2022/2581Lawamends

    … от разпоредбите на член 6, член 7, параграф 1, член 8, параграфи 1 и 4, членове 9, 10 и 11 от Регламент (ЕС) 2019/943 и от член 40, параграфи 4—7 от …

  • Judgment of the Court (Fifth Chamber) of 2 March 2023. Bursa Română de Mărfuri SA v Autoritatea Naţională de Reglementare în domeniul EnergiDecision

    Article 10 of that regulation, entitled ‘Technical bidding limits’, states: ‘1. There shall be neither a maximum nor a minimum limit to the wholesale electricity price. … … 4. Regulatory authorities or … designated competent …

    2 Mar 2023 · 62021CJ0394

  • Conclusions de l'avocat général M. A. Rantos, présentées le 25 juin 2026.Decision

    … for dette afgrænsede forslag til afgørelse: »4) Skal bestemmelserne i artikel 3, litra a), b), h) og p), samt artikel 10, stk. 1, 4 og 5, i forordning 2019/943 [...], sammenholdt med 22. og 23. betragtning hertil, i artikel 5, stk. 1, 3 …

    25 Jun 2026 · 62024CC0251

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 June 2025. RWE Supply & Trading GmbH v European Union Agency for tDecision

    … изтъква шест основания по същество, а именно, първо, нарушение на член 10, параграф 1 от Регламент 2019/943, второ, липса на компетентност …

    25 Jun 2025 · 62023TJ0095

  • Judgment of the Court (Ninth Chamber) of 22 October 2026. „VETS Svoge“ EOOD v Predsedatel na Upravitelnia savet na Fond „Sigurnost na elektrDecision

    … 82), на член 3, букви а), б), з) и п) и на член 10, параграфи 1, 4 и 5 от Регламент (ЕС) 2019/943 на Европейския парламент и на Съвета от 5 юни 2019 …

    22 Oct 2026 · 62025CJ0327