Art. 28 Regulation (EU) 2019/942

Decisions subject to appeal

In forcesince 5 Jun 2019cited 32×
1.

Any natural or legal person, including the regulatory authorities, may appeal against a decision referred to in point (d) of Article 2 which is addressed to that person, or against a decision which, although in the form of a decision addressed to another person, is of direct and individual concern to that person.

2.

The appeal shall include a statement of the grounds for appeal and shall be filed in writing at ACER within two months of the notification of the decision to the person concerned, or, in the absence thereof, within two months of the date on which ACER published its decision. The Board of Appeal shall decide upon the appeal within four months of the lodging of the appeal.

3.

An appeal lodged pursuant to paragraph 1 shall not have suspensory effect. The Board of Appeal may, however, if it considers that circumstances so require, suspend the application of the contested decision.

4.

If the appeal is admissible, the Board of Appeal shall examine whether it is well-founded. It shall invite the parties to the appeal proceedings as often as necessary to file observations on notifications issued by itself or on communications from the other parties to the appeal proceedings, within specified time limits. Parties to the appeal proceedings shall be entitled to make an oral presentation.

5.

The Board of Appeal may confirm the decision, or it may remit the case to the competent body of ACER. The latter shall be bound by the decision of the Board of Appeal.

6.

ACER shall publish the decisions taken by the Board of Appeal.

The 10 that are cited most themselves, of 32.

  • Judgment of the General Court (Second Chamber, Extended Composition) of 7 September 2022. Bundesnetzagentur für Elektrizität, Gas, TelekommuDecision

    Third, in relation to the requirements for bringing an action for annulment before the Court of Justice of the European Union against both the initial decision and the decision of the Board of Appeal, it follows from Article 28(1) and …

    7 Sep 2022 · 62019TJ0631

  • Judgment of the Court (Fifth Chamber) of 9 March 2023. European Union Agency for the Cooperation of Energy Regulators v Aquind Ltd.Decision

    As regards ACER’s argument based on the brevity of the time limit for the Board of Appeal to give a decision, set at two months by Article 19(2) of Regulation No 713/2009, it cannot be inferred from this that the intention of the EU …

    9 Mar 2023 · 62021CJ0046

  • Judgment of the General Court (Second Chamber, Extended Composition) of 16 March 2022. Magyar Energetikai és Közmű-szabályozási Hivatal (MEKDecision

    In the second place, it follows from recital 34 and from Articles 28 and 29 of Regulation 2019/942 that natural and legal persons disagreeing with a decision of ACER that is addressed to them or is of individual and direct concern to them …

    16 Mar 2022 · 62019TJ0684

  • Regulation (EU) No 1227/2011 of the European Parliament and of the Council of 25 October…13a13b13gLaw

    … Чрез дерогация от членове 28 и 29 от Регламент (ЕС) 2019/942 решението на Агенцията подлежи на контрол единствено от страна на Съда.

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 15 September 2022. European Union Agency for the Cooperation of Energy RegulDecision

    Article 19 [I have reproduced the version of this article that was in force at the time of the dispute. Its equivalent in Regulation 2019/942 is Article 28, paragraph 5 of which states that ‘the Board of Appeal may confirm the decision, …

    15 Sep 2022 · 62021CC0046

  • Judgment of the General Court (Second Chamber) of 15 February 2023. Aquind Ltd and Others v European Union Agency for the Cooperation of EneDecision

    … е изведено от нарушение на изискванията на член 25, параграф 3 и на член 28, параграф 4 от Регламент (ЕС) 2019/942 на Европейския парламент …

    15 Feb 2023 · 62021TJ0492

  • Judgment of the General Court (Third Chamber, Extended Composition) of 8 October 2025. Swissgrid AG v European Union Agency for the CooperatDecision

    … съвет на ACER Специфични условия и правила относно жалбите Член 28 от Регламент (ЕС) 2019/942 Недопустимост поради липса на процесуална …

    8 Oct 2025 · 62023TJ0556

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Bundesnetzagentur für Elektrizität, Gas, TelekommuDecision

    The powers available to ACER to adopt the contested cost sharing methodology are thus precisely delineated and amenable, in accordance with Articles 28 and 29 of Regulation 2019/942, to judicial review in the light of the objectives …

    25 Sep 2024 · 62021TJ0485

  • Judgment of the General Court (Second Chamber, Extended Composition) of 15 February 2023. Austrian Power Grid AG and Others v European UnionDecision

    На 23 март 2020 г., в съответствие с член 28 от Регламент (ЕС) 2019/942 на Европейския парламент и на Съвета от 5 юни 2019 година за създаване на …

    15 Feb 2023 · 62020TJ0606

  • Regulation (EU) 2022/86916Law

    … Прилагат се член 25, параграф 3 и членове 28 и 29 от Регламент (ЕС) 2019/942. 8. Агенцията незабавно изпраща на Комисията копия на всички …