Art. 13 Regulation (EU) 2019/473

Procedure for the adoption of joint deployment plans

In forcesince 19 Mar 2019
1.

On the basis of the notifications provided for in Article 12(2) and within three months of the receipt of such notifications, the Executive Director of the Agency shall establish a draft joint deployment plan in consultation with the Member States concerned.

2.

The draft joint deployment plan shall identify the means of control and inspection which could be pooled in order to implement the control and inspection programme that the plan relates to, on the basis of the interest of the Member States concerned in the relevant fishery.

The interest of a Member State in a fishery shall be assessed by reference to the following criteria whose relative weighting shall depend on the specific features of each plan:

(a)

the relative extent of the waters subject to its sovereignty or jurisdiction, if any, that are covered by the joint deployment plan;

(b)

the quantity of fish landed on its territory in a given reference period as a proportion of the total landings from the fishery that is subject to the joint deployment plan;

(c)

the relative number of Union fishing vessels flying its flag (engine power and gross tonnage) that are involved in the fishery that is subject to the joint deployment plan in relation to the total number of vessels that are involved in that fishery;

(d)

the relative size of its quota allocation or, in the absence of a quota, its catch in a given reference period in respect of that fishery.

3.

If, in the course of preparing a draft joint deployment plan, it is apparent that there are insufficient means of control and inspection available to fulfil the requirements of the relevant control and inspection programme, the Executive Director shall promptly notify the Member States concerned and the Commission.

4.

The Executive Director shall notify the draft joint deployment plan to the Member States concerned and the Commission. If, within fifteen working days of such notification, the Member States concerned or the Commission have not raised any objection, the Executive Director shall adopt the plan.

5.

If one or more of the Member States concerned or the Commission has raised an objection, the Executive Director shall refer the matter to the Commission. The Commission may make any necessary adjustments to the plan and adopt it in accordance with the procedure referred to in Article 47(2) of Regulation (EU) No 1380/2013.

6.

Each joint deployment plan shall be subject to an annual review by the Agency in consultation with the Member States concerned to take account of any new control and inspection programmes which the Member States concerned are subject to and any priorities determined by the Commission in the control and inspection programmes.