Art. 43v Regulation (EU) 2018/2067

Site visits and simplified verification

In forcesince 1 Jan 2025cited 2×
1.

At one or more appropriate times during the verification process, the verifier shall conduct a site visit in order to assess the operation of measuring devices and monitoring systems, to conduct interviews, to carry out the activities required by this Chapter as well as to gather sufficient information and evidence enabling it to conclude whether the regulated entity’s report is free from material misstatements.

When carrying out site visits in accordance with the first subparagraph, the verifier shall also assess the completeness of released fuel streams and released fuel amounts.

2.

The regulated entity shall provide the verifier access to its sites.

3.

For the purposes of verifying the regulated entity’s emission report, the verifier shall decide, based on the risk analysis, whether visits to additional locations are needed, including where relevant parts of data flow activities and control activities are carried out in other locations such as company headquarters and other off-site offices.

4.

By way of derogation from paragraph 1, the verifier may decide not to carry out site visits to regulated entities. This decision shall be based on the following criteria:

(a)

the outcome of the risk analysis;

(b)

the confirmation that all relevant data can be remotely accessed by the verifier;

(c)

the confirmation that the relevant conditions for not carrying out the site visits, pursuant to Article 43w of this Regulation are met;

(d)

the confirmation that the mandatory site visits, pursuant to paragraph 7 of this Article, are not applicable to that regulated entity.

The verifier shall inform the regulated entity of its decision without undue delay.

5.

The regulated entity shall submit an application to the competent authority requesting the competent authority to approve the verifier’s decision not to carry out the site visit. The application shall at least consist of the following information:

(a)

the outcome of the risk analysis;

(b)

evidence that the relevant data can be remotely accessed;

(c)

evidence that the relevant conditions for not carrying out the site visits, pursuant to Article 43w of this Regulation, are met;

(d)

evidence that the mandatory site visits, pursuant to paragraph 7 of this Article, are not applicable to that regulated entity.

The approval of the competent authority shall not be required for regulated entities with low emissions, as specified in Article 75n(1) of Implementing Regulation (EU) 2018/2066.

6.

Taking into account the information referred to in paragraph 5, points (a) to (d), the competent authority shall decide whether or not to approve the verifier’s decision not to carry out the site visit.

Where the competent authority has not replied to the application from the regulated entity, in accordance with paragraph 5 within two months upon its receipt, the verifier’s decision is considered approved.

7.

The verifier shall always carry out site visits in the following situations:

(a)

a regulated entity’s report is verified for the first time by the verifier;

(b)

no site visit has been carried out by a verifier in the two reporting periods immediately preceding the current reporting period;

(c)

significant modifications of the monitoring plan, in accordance with Article 75b(3) of Implementing Regulation (EU) 2018/2066, were made during the reporting period.

  • EHV 203032Law

    … und 2026 in Verkehr gebracht werden, gilt zur Vereinfachung der Verifizierung der Antrag des Verantwortlichen gemäß Artikel 43v Absatz 5 Satz 1 und 2 der Durchführungsverordnung (EU) 2018/2067 bei der zuständigen Behörde auf Erteilung …

  • EHV 203032Law