Where the implementation of recommendations referred to in Article 17a of this Regulation has not been completed, the verifier shall assess the operator’s evidence and check whether:
the energy efficiency recommendations referred to in Article 22a(1), second subparagraph, point (f), of Delegated Regulation (EU) 2019/331 were not issued in the first four years of the baseline period;
recommendations would not lead to energy savings within the system boundaries of the industrial process carried out at the installation;
the pay-back time referred to in Article 22a(1), second subparagraph, point (a), of Delegated Regulation (EU) 2019/331 exceeds three years;
the installation specific operating conditions, including planned or unplanned periods of maintenance, upon which the pay-back period was determined have not yet occurred;
the investment costs of the recommendations exceed the thresholds listed in Article 22a(1), second subparagraph, point (b) of Delegated Regulation (EU) 2019/331;
other measures have been implemented during or after the relevant baseline period which led to greenhouse gas emission reductions equivalent to those recommended by the energy audit report or a certified energy management system for the installation.
Where the pay-back time referred to in Article 22a(1), second subparagraph, point (a), of Delegated Regulation (EU) 2019/331 is not specified in the energy audit report, the certified energy management system or a sworn declaration from the energy auditor, the verifier shall check:
the validity of the information used to determine the pay-back time;
the correct application of the method used to determine the pay-back time.
For the purpose of assessing implementation of measures referred to in paragraph 1, point (f), the verifier shall check and confirm whether:
the operator has implemented the alternative measures and whether the implementation of those measures has been completed;
equivalent greenhouse gas emission reductions referred to in paragraph 1, point (f), have been achieved.