Art. 25 Regulation (EU) 2017/460

Conditions for offering payable price approaches

In forcesince 16 Mar 2017
1.

Where and to the extent that the transmission system operator functions under a non-price cap regime, the conditions for offering payable price approaches shall be as follows:

(a)

for cases where only existing capacity is offered:

(i)

the floating payable price approach shall be offered;

(ii)

the fixed payable price approach shall not be allowed.

(b)

for incremental capacity and existing capacity offered in the same auction or same alternative allocation mechanism:

(i)

the floating payable price approach may be offered;

(ii)

the fixed payable price approach may be offered where one of the following conditions is met:

(1)

an alternative allocation mechanism set out in Article 30 of Regulation (EU) 2017/459 is used;

(2)

a project is included in the Union list of projects of common interest as set out in Article 3 of Regulation (EU) No 347/2013 of the European Parliament and of the Council [Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC and amending Regulations (EC) No 713/2009, (EC) No 714/2009 and (EC) No 715/2009 (OJ L 115, 25.4.2013, p. 39).].

2.

Where and to the extent that the transmission system operator functions under a price cap regime, the floating payable price approach or the fixed payable price approach, or both, may be offered.