As regards Bulgaria, the assessment showed that the revised targets are based on a planned reduction of its en route determined unit costs over the second reference period by 1,1 % per year on average. This is below the targeted reduction of the average Union-wide en route determined unit costs over that period. However, over the combined period of the first and the second reference period the planned en route determined unit costs decrease at a higher rate (– 2,3 %) than the Union-wide target. Furthermore, Bulgaria's revised target for 2019 is based on planned en route determined unit costs that are below (3,0 %) the average en route determined unit costs of Member States having a similar operational and economic environment to the one of Bulgaria. The Commission therefore considers that the revised targets of Bulgaria for the years 2017, 2018 and 2019 are consistent with the Union-wide targets in the key performance area of cost-efficiency for the second reference period.
Recital 7, Decision_act (EU) 2017/2376
In forcesince 15 Dec 2017